All over the world, architects are finding cool ways to re-use run-down old buildings. Click here to see the best in Refurbishment Architecture.

Want to see the coolest refurbishment projects? Click here.

i

Immerse yourself in inspiring buildings with our selection of 360 videos. Click here.

See our immersive, inspiring 360 videos. Click here.

All
Projects
Products
Events
Competitions
Navigate articles using your keyboard
  1. ArchDaily
  2. Projects
  3. Landscape Architecture
  4. Australia
  5. AIA Architectes
  6. 2012
  7. The Victorian Desalination Project & Ecological Reserve / AIA Architectes + ASPECT Studios

The Victorian Desalination Project & Ecological Reserve / AIA Architectes + ASPECT Studios

  • 17:00 - 24 July, 2017
The Victorian Desalination Project & Ecological Reserve / AIA Architectes + ASPECT Studios
The Victorian Desalination Project & Ecological Reserve / AIA Architectes + ASPECT Studios, © John Gollings
© John Gollings

© Peter Bennetts © Peter Bennetts © Peter Bennetts © Peter Bennetts + 15

© Peter Bennetts
© Peter Bennetts

Text description provided by the architects. The Victorian Desalination Project is critical infrastructure for climate adaption and one of the largest such investments in Australia's history. The 225 ha Ecological Reserve camouflages the Project through a 26000m2 green roof and a dune system evolved from spoil, transforms the degraded land into mosaics of coastal and swampy woodlands. Wetlands and dune ecologies reconnect remnants and provide rich visitor experience.

Site Plan
Site Plan

Landscape architects from ASPECT Studio led the site plan to ensure an ecologically resilient landscape. Their 3D site master-model allowed cross disciplinary testing to create outcomes not otherwise possible in a project of this complexity. Such leadership proves new roles for the profession.

© Peter Bennetts
© Peter Bennetts

Local seed collection and onsite propagation established millions of plants. The green roof's 25 species required significant research to establish a local palette suitable for predicted future conditions. It has purpose-designed lightweight high water retention planting media and integrated growth support systems. The Reserve uses only on-site water capture. Traditional Owner cultural values informed design.

Historical Original Zone
Historical Original Zone
Original Vegetation Zone
Original Vegetation Zone

Amenity includes 8km of pedestrian, cyclist and equestrian trails, wayfinding, interpretation, boardwalks, bird hide, viewing decks and picnic shelters.

© Peter Bennetts
© Peter Bennetts
© Peter Bennetts
© Peter Bennetts
© Peter Bennetts
© Peter Bennetts

The project has returned local fauna, including endangered species and internationally significant migratory birds. It has advanced green roof design. A mandated 18-year review ensures ecological values are maintained into the future.

Proposed Vegetation Zone
Proposed Vegetation Zone

Central to the project is the regeneration of the former agricultural and mining landscape into an ecologically diverse landscape. This will take time. The planting commenced in 2010 and seven years in we are seeing the successful establishment of many of the small trees, shrubs, grasses, and groundcovers planted as seedlings and the overall low ground coverage of the vast areas of constructed dunes and landscape plans. The resultant vegetation community is a complex mix of life forms including ground cover, understory, front line coastal, fresh and brackish wetlands, and woodland canopy. This landscape will continue to evolve and change, as our weather patterns changes and it moves from a constructed landscape to one of natural redistribution and regeneration. Given this, time is essential in achieving a fully established landscape equivalent of one that would have been naturally occurring, which is expected to reach maturity around 2030.

© Peter Bennetts
© Peter Bennetts

View the complete gallery

Location to be used only as a reference. It could indicate city/country but not exact address.
About this office
AIA Architectes
Office
Cite: "The Victorian Desalination Project & Ecological Reserve / AIA Architectes + ASPECT Studios" 24 Jul 2017. ArchDaily. Accessed . <https://www.archdaily.com/876189/the-victorian-desalination-project-and-ecological-reserve-aspect-studios/> ISSN 0719-8884
© John Gollings

维多利亚海水淡化项目和生态保护区 / AIA Architectes + ASPECT Studios